East Washington St is On Schedule

Sanitary sewer is complete from Pike to the Circle. Storm sewer is nearing completion in the same area. Sidewalk has started to be poured from the circle heading east. Curb and gutter continues to be installed from the circle heading east.
Weather has been very favorable for construction so things are ahead of schedule and we hope to keep that progressing.  (Note:  With so much project left, we’re not going to update the overall schedule and just consider the project “on time” at this point.)

Duke Energy and the inspector are currently looking at installing electric outlets along the road for events.