Progress on Sidewalk & Curb and New Project Timeline

The sidewalk on the north side of the road is complete from the circle to Honey & Henry’s, with the exception of a 30 ft section that is waiting on the installation of a limestone wall.  The wall will allow for proper ADA compliance in front of 20 East Washington St.

The curb and gutter on the north side of the road is complete from the Public Square to Pike Street.

The schedule on the webpage has been updated, and a new project timeline has been added.  Check marks can be seen on the timeline where different phases are complete.  There are no real changes to the schedule, other than the sidewalk on the south side of the road will all be done at the same time.