East Washington Street

General Project Timeline

NOTE:  This is general construction schedule and could change as project goes forward, and there can be more than one stage going on at the same time.  
  • From April to June, North Side Sanitary Work from SR 9 to Pike 
  • From June to July, North Side Sanitary Work from Pike to RR   
  • From May to July, North Side Storm Sewer and Hardscape Work from SR 9 to Pike
  • From April to June, Sidewalk Near Buildings South Side of SR 9 to Pike
  • From July to August, Sidewalk Near Road and Bumpouts South Side of SR 9 to Pike
By September 30, All Hardscape work completed (and traffic opened)  from SR 9 to Pike
  • From August to November, Sidewalk Near Buildings South Side from Pike to RR
  • From November to December, Sidewalk Near Road and Bumpouts South Side from Pike to RR
  • From September to October, Landscaping from SR 9 to Pike
By December 6, all Hardscape work completed (and traffic opened) from Pike to RR
  • By May of 2020, all Landscaping work completed from Pike to RR

Documents

Contact Info

For questions about the East Washington St Project, such as access, construction, or traffic concerns, contact Tom Zimmer at tzimmer@zimmerce.com.     

Traffic Detour Information

Above is the traffic control map for the East Washington Street Project.  Throughout the construction process, portions of East Washington Street will be restricted to one-way traffic only to the east, as shown above. 

Drivers should remember that Franklin St and Jackson St are also one-way to the east from the Public Square to Noble St.  The decision to make the traffic on East Washington St a one-way to the east based on requests from the business owners.

Project Updates

As the East Washington Street Project progresses, City Staff will be posting updates on the status of the project below:

Sewer work begins, businesses remain open!

April 22, 2019

Sewer work begins, businesses remain open!

Excavation work began today on the northern half of the street so that the sanitary sewer lines in the area can be upgraded to better…

Read more

Installation of Construction Barriers and Signage

April 16, 2019

Installation of Construction Barriers and Signage

Beaty Construction will be installing all of the traffic control devices and construction barriers in preparation of the construction. A map of the detour routes…